Background: COVID-19 exposed the need to reevaluate how we fundamentally approach and accomplish UX, technical and web development-related work.
The success of digital transformation initiatives is critical to achieving strategic goals throughout the organization. Process improvements supported by a project management tool configured to meet our unique needs can help optimize department resources, streamline workflows and enable reporting to track progress, productivity, and ensure nothing slips.
Reference materials:
Scope
Implement process improvements that are optimized for the current remote work environment.
Implement a suite of tools for project management, resource management and capacity planning.
Take a phased approach to implementing tool use by the entire marketing team.
Roadmap phases, measuring results at a regular frequency and setting goals for process, workflow and feature improvements at designated milestones.
📋 Summary
Current project health | Completed | This week (6/1) | Next week (6/8) |
---|---|---|---|
GREEN |
|
|
|
📊 Timeline
Phase | Tasks | Timeframe |
I | Work through task types, project types, roadmap setup, and other infrastructure. Track major efforts related to Back to Practice and COVID-19, along with website tasks Track time related to these projects | June 1: Set up vendor access in Jira June 15: Track Back to Practice, COVID, and website tasks in Jira, as well as time. June 30: Review logged time report from June 15-30 |
II | Other teammates/projects begin using Jira and tracking time on tasks. Work with the team to ensure smooth transition and adjust setup as necessary. | July 15: Set up projects for publications and communications (content team projects) Trials for estimating time |
III | Teammates begin estimating time for future work. Begin exploration of forecasting and planning app. | July 30: Set up projects for the design team Officially begin estimating time August 1-15: Set up TDIC, TDSC, Foundation, and any other Basecamp projects Review planned vs logged time reports |
IV | Review data and survey team. Continue iterative improvements to setup as needed. | August 16-30: Review |
Task Status
Note: Must be logged into Jira to view.