TDIC Alternate Timeline
Phase 3: Execution - Design | 12/02/20 | 03/13/21 | |
Part 1: Discovery | 17d | 12/02/20 | 12/19/20 |
User research | 2d | 12/02/20 | 12/04/20 |
Competitive analysis | 2d | 12/04/20 | 12/06/20 |
Content audit | 10d | 12/06/20 | 12/16/20 |
Prepare findings for stakeholder presentation | 1d | 12/04/20 | 12/05/20 |
Stakeholder review & approval | 2d | 12/05/20 | 12/07/20 |
Part 2: UX Strategy | 31d | 12/07/20 | 01/07/21 |
Stakeholder workshop: Content prioritization | 2d | 01/07/21 | 01/09/21 |
Information architecture | 7d | 01/09/21 | 01/16/21 |
Stakeholder workshop: User journeys and Task Flows | 1d | 01/16/21 | 01/17/21 |
User Journeys | 7d | 01/17/21 | 01/24/21 |
Content strategy | 7d | 12/16/20 | 12/23/20 |
Metadata | 7d | 12/23/20 | 12/30/20 |
Part 3: UX Design | 24d | 12/30/20 | 01/23/21 |
Task Flows | 7d | 12/30/20 | 01/06/21 |
Low-fidelity wireframes | 7d | 01/06/21 | 01/13/21 |
Content revisions | 3d | 01/13/21 | 01/16/21 |
Low-fidelity prototypes | 4d | 01/16/21 | 01/20/21 |
User focus groups and/or testing | 3d | 01/20/21 | 01/23/21 |
Part 4: Production Visual Design & Development | 28d | 01/23/21 | 02/20/21 |
UI Kit / Design System / Branding | 7d | 02/20/21 | 02/27/21 |
2sxc Component Design | 7d | 01/23/21 | 01/30/21 |
Visual elements (photography and video) | 7d | 02/27/21 | 03/06/21 |
High-fidelity mockups/prototypes | 7d | 03/06/21 | 03/13/21 |
Additional Risks
Azure implementation scheduled to happen before deployment
Project charter mentions video content and photo content to be developed in parallel to this work; is this to be outsourced to a separate team, or are we allocating additional resources for this?
Resource allocation is limited for TDIC: will we have additional staff that can help with UX, content strategy, design and implementation?
Notes from meeting:
Identified additional resources:
100% Aline allocation
100% Shelly allocation
Person to comb through content
Person to build pages
Person to work on tag manager